Handle Diesel Generator Balloon Project Light Tower with Direct Injection Diesel Engine
Contact Person : Roger Xie
Phone Number : +86 13533071813
WhatsApp : +8613533071813
Minimum Order Quantity : | 1 Set | Price : | Negotiable |
---|---|---|---|
Packaging Details : | Standard Wooden Case or as customer requirement | Delivery Time : | 15 days after receiving your TT deposit |
Payment Terms : | 30% T / T in advance and 70% balance before shipment / 100% L / C at sight | Supply Ability : | 20 Set Per Month |
Place of Origin: | Guangdong China | Brand Name: | Laurel |
---|---|---|---|
Certification: | CE | Model Number: | LFSYD15 |
Detail Information |
|||
Frequency: | 50Hz/ 60Hz | Speed: | 1500rpm / 1800rpm |
---|---|---|---|
Rated Power: | 15KW | Rated Voltage: | 230V / 400 V |
Rated Current: | 27A | Power Factor: | 0.8 Lag |
Stroke: | 4 | Cooling Method: | Water Cooling |
High Light: | Diesel Powered Generator,Diesel Power Generator Set |
Product Description
15Kw Open Diesel Generator Set Made from Manufacturer Water Cooling 4 Stroke
Product details:
Conditions of Use: Land Use
Landuse Type of Unit: Ordinary
Condition: New
Dimension: 1950*900*1050(mm)
Type of Governor: Mechanical
Protection Grade: IP23
Specifications:
Product Configuration-18.75KVA Geneset |
||||
Model |
LFSYD15 |
|
Rate Votage |
230V/400V or as your demand |
Prime power |
15kw 21kva |
Standby power |
18.75kw 26.25kva |
|
Frequency |
50/60Hz |
Speed |
1500/1800rpm |
|
Size(mm) |
1950*900*1050 |
Genset set weight |
About750kg |
Specification of Laurel Engine |
||||
Model |
HR490D |
|
Frequency control ways |
machinery |
Total displacement |
2.54 L |
|
Rated fuel consumption |
247.5g/KW.h |
Compression rate |
18:1 |
|
Cylinder bore/stroke(mm) |
4-90×100 |
Specification of Alternator |
||||
Protection grade |
IP23 |
|
Insulation grade |
H degree |
Compression rate |
18:1 |
Over speed capacity |
2250min-1 |
|
Phase |
3 phases,4 wires |
EMI efficient |
THF<2%,TIF<50 |
Our Services:
Diesel generator set/Gas generator set/Alternator: 12 months from shipment date.
Gasoline generator set: 6 months from shipment date.
Spare parts: 3 months from shipment date.
Factory Inspection:
the test items before delivery are mainly as follows:
1. Each genset shall be put into commission more than 4 hours totally. They are tested on idle load,fully load and 10% overload;
2. The noise level is tested
3. All of the meters on the control panel shall be tested
4. The appearance of the genset and all of the label and nameplate shall be checked